Highway works with the AWE Redevelopment Print E-mail
Written by Barbara Payne   
Tuesday, 08 January 2008

AWE Redevelopment Programmed Highway Works

The Highway works are being split into 5 phases  and each phase will include the construction of a new road junction either in the form of a roundabout or traffic signals.
The Phases are
Phase 1  Tadley Gate and Aldermaston Gate Roundabouts together with a Toucan Crossing at the Tadley Gate junction
Phase 2 A340 Aldermaston Hill Roundabout at the Young's Industrial Estate entrance
Phase 3 AWE Main Gate roundabout together with toucan Crossing and cycleway scheme
Phase 4 Falcon Gyratory signalising together with Toucan Crossing
Phase 5 Heath End Road Roundabout adjustment.
 
Phase 1 is programmed to start week commencing 7th January 2008 with the carriageway being affected from the 21st January 2008 for 15 weeks.
The remaining Phases will then follow one at a time with each one expected to take 16 weeks from start to finish. ( due to possible construction programming there may be more than one phase happening at the same time).
The completion date for all 5 Phases is currently programmed to be the end of April 2009.

Information kindly provided by the Tadley Town Council

www.tadleycouncil.org

Any comments about local issues, housing, roadworks, policing etc, please drop us an email at This e-mail address is being protected from spam bots, you need JavaScript enabled to view it

 

 
Tadley Roundabout is designed and maintained by Tadley Web Design

Private Login


All Content © 2008 Tadley Roundabout unless stated otherwise.